CUP: H81B06004340002
POTENZIAMENTO DEL SISTEMA DI MOBILIT URBANA PER L'ADEGUAMENTO DEI FLUSSI DI TRAFFICO IN ENTRATA/USCITA DALLE AREE PRODUTTIVE. AGROPOLI - CAPACCIO
SUMMARY OF THE PROJECT
POTENZIAMENTO DEL SISTEMA DI MOBILIT URBANA PER L'ADEGUAMENTO DEI FLUSSI DI TRAFFICO IN ENTRATA/USCITA DALLE AREE PRODUTTIVE. AGROPOLI - CAPACCIO
Implementation indicator
Estensione in lunghezza
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 1,391,082.64
of which cohesion funds
€ 1,391,082.64
Given name | Amount |
---|---|
Development and Cohesion Fund | 1391082.64 |
Payments monitored
€ 743,160.00
of which cohesion funds
€ 743,160.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 743160.00 | 743160.00 | 53 |
State of progress
Open
Expected start: 20/07/2009
Effective start: 20/07/2009
Expected end: 21/01/2011
Effective end: 16/12/2010
Entities
- Planning body
- AMMINISTRAZIONE PROVINCIALE DI SALERNO
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI SALERNO
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI SALERNO
Programming area
- Programme
- PSC CAMPANIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,391,082.64
- Payments on cohesion funds
- € 743,160.00
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici