This project is eliminated from views and totals because it is a duplicate of the project:
Updated on 31/12/2024
Funding monitored € 14,930,780.65 of which cohesion funds € 2,196,894.11
Given name Amount
European Union10953199.08
Development and Cohesion Fund2196894.11
Province495883.28
Another public source1284804.18
Payments monitored € 14,930,780.58 of which cohesion funds € 2,196,894.10
Year Amount Cumulative amount Percentage on public financing
20035890.905890.900
200413090.2018981.100
20056760.0025741.100
2006256847.27282588.371
2007861919.371144507.747
20084082145.095226652.8335
20094632792.609859445.4366
20102683611.1312543056.5684
20111201604.2013744660.7692
20121044607.0714789267.8399
201373575.7014862843.5399
201467937.0514930780.5899

State of progress

Completed
Expected start: 21/09/2007
Effective start: 21/09/2007
Expected end: 31/10/2011
Effective end: 31/10/2011

Type

Theme

Territory

Entities

Planning body
REGIONE CALABRIA
Implementing body
AMMINISTRAZIONE PROVINCIALE DI CROTONE
Beneficiary
REGIONE CALABRIA

Programming area

Programme
PSC REGIONE CALABRIA
Fondo Aree Sottoutilizzate 2000-2006
2000-2006 Underutilized Areas Fund
Cohesion funds
€ 2,196,894.11
Payments on cohesion funds
€ 2,196,894.10
Policy Area
Trasporti e Mobilita'
Sector of intervention
Trasporto stradale