CUP: H33C07000010002
Lavori di realizzazione della rete fognaria delle zone rurali e del PIP - Primo stralcio
SUMMARY OF THE PROJECT
Lavori di realizzazione della rete fognaria delle zone rurali e del PIP - Primo stralcio
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 611,805.50
of which cohesion funds
€ 611,805.50
Given name | Amount |
---|---|
Development and Cohesion Fund | 611805.50 |
- Economies:
- € 21,269.73
Payments monitored
€ 611,805.50
of which cohesion funds
€ 611,805.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 235374.00 | 235374.00 | 38 |
2010 | 81163.00 | 316537.00 | 51 |
2011 | 283025.10 | 599562.10 | 97 |
2012 | 12243.40 | 611805.50 | 100 |
State of progress
Completed
Expected start: 11/02/2008
Effective start: 11/02/2008
Expected end: 05/11/2010
Effective end: 05/11/2010
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- COMUNE DI CHIARAVALLE CENTRALE
- Beneficiary
- REGIONE CALABRIA
Programming area
- Programme
- PSC REGIONE CALABRIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 611,805.50
- Payments on cohesion funds
- € 611,805.50
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e servizi