CUP: H33J06000040002
INTERVENTI DI RAZIONALIZZAZIONE, EFFICIENTAMENTO, COMPLETAMENTO RETI IDRICHE DI DISTRIBUZIONE DEL COMUNE
SUMMARY OF THE PROJECT
INTERVENTI DI RAZIONALIZZAZIONE, EFFICIENTAMENTO, COMPLETAMENTO RETI IDRICHE DI DISTRIBUZIONE DEL COMUNE
Implementation indicator
Ampliamento lunghezza rete
- Target
- 300 m
- Achieved
- 300 m
Download project
Funding monitored
€ 208,177.23
of which cohesion funds
€ 149,602.31
Given name | Amount |
---|---|
European Union | 58574.92 |
Development and Cohesion Fund | 149602.31 |
- Economies:
- € 49,822.77
Payments monitored
€ 208,177.23
of which cohesion funds
€ 149,602.29
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 118667.74 | 118667.74 | 57 |
2009 | 5497.80 | 124165.54 | 59 |
2010 | 84011.69 | 208177.23 | 100 |
State of progress
Completed
Expected start: 28/07/2008
Effective start: 28/07/2008
Expected end: 29/05/2009
Effective end: 29/05/2009
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- COMUNE DI PENTONE
- Beneficiary
- REGIONE CALABRIA
Programming area
- Programme
- PSC REGIONE CALABRIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 149,602.31
- Payments on cohesion funds
- € 149,602.29
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche