CUP: J63H01000000006
RIORDINO IMPIANTO IRRIGUO A VALLE DELLA DIGA FARNETO DEL PRINCIPE - 3^ LOTTO - AGRO DI ROGGIANO G. - CASTROVILLARI - TARSIA - S.LORENZO DEL VALLO - SPEZZANO A.
SUMMARY OF THE PROJECT
RIORDINO IMPIANTO IRRIGUO A VALLE DELLA DIGA FARNETO DEL PRINCIPE - 3^ LOTTO - AGRO DI ROGGIANO G. - CASTROVILLARI - TARSIA - S.LORENZO DEL VALLO - SPEZZANO A.
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 10,366,564.28
of which cohesion funds
€ 10,366,564.28
Given name | Amount |
---|---|
Development and Cohesion Fund | 10366564.28 |
- Economies:
- € 639,196.17
Payments monitored
€ 10,366,564.28
of which cohesion funds
€ 10,366,564.28
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2003 | 239466.83 | 239466.83 | 2 |
2004 | 3233095.14 | 3472561.97 | 33 |
2005 | 3106732.32 | 6579294.29 | 63 |
2006 | 1260918.33 | 7840212.62 | 75 |
2007 | 4027.58 | 7844240.20 | 75 |
2008 | 13303.94 | 7857544.14 | 75 |
2009 | 758899.35 | 8616443.49 | 83 |
2010 | 1750120.79 | 10366564.28 | 100 |
State of progress
Completed
Expected start: 17/04/2003
Effective start: 17/04/2003
Expected end: 12/04/2008
Effective end: 12/04/2008
Entities
- Planning body
- REGIONE CALABRIA
- Implementing body
- REGIONE CALABRIA
- Beneficiary
- REGIONE CALABRIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE CALABRIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche