CUP: D52I16000500001
RIQUALIFICAZIONE DI VIA SOLFERINO E VIA CASTELFIDARDO
SUMMARY OF THE PROJECT
IL PROGETTO HA IL DUPLICE OBIETTIVO DI RIQUALIFICARE IL PARCO LAMA BALICE PER RENDERLO ACCESSIBILE E FRUIBILE ATTRAVERSO LA REALIZZAZIONE DI PERCORSI CICLO-PEDONALI E DI SPAZI DA ADIBIRE A SERVIZI PER I VISITATORI NEL COMUNE DI BITONTO ED AL CONTEMPO REALIZZARE ALLESTIMENTI ITINERANTI PER DESCRIVERE GLI ATTRATTORI NATURALI E CULTURALI DELLA CITTA METROPOLITANA DI BARI ATTRAVERSO TECNOLOGIE INNOVATIVE.
Implementation indicator
Investimenti totali
- Target
- 1,800,000 euro
- Achieved
- 83,787.67 euro
Funding monitored
€ 1,950,000.00
of which cohesion funds
€ 1,950,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1950000.00 |
Payments monitored
€ 104,624.14
of which cohesion funds
€ 104,624.14
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 15930.69 | 15930.69 | 0 |
2021 | 22675.91 | 38606.60 | 1 |
2022 | 62411.55 | 101018.15 | 5 |
2023 | 3605.99 | 104624.14 | 5 |
State of progress
Open
Expected start: 01/07/2020
Effective start: not available
Expected end: 30/10/2021
Effective end: not available
Entities
- Planning body
- CITTA METROPOLITANA DI BARI
- Implementing body
- COMUNE DI BITONTO
- Beneficiary
- CITTA METROPOLITANA DI BARI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CITTA' METROPOLITANA DI BARI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico