CUP: H69J21004230002
Reti verdi urbane Comuni di TRICARICO- SAN CHIRICO- NUOVO-TOLVE
SUMMARY OF THE PROJECT
Reti verdi urbane Comuni di TRICARICO- SAN CHIRICO- NUOVO-TOLVE
Implementation indicator
Superficie oggetto di intervento
- Target
- 20,000 mq
- Achieved
- 0 mq
Download project
Funding monitored
€ 500,000.00
of which cohesion funds
€ 500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 500000.00 |
Payments monitored
€ 168,491.92
of which cohesion funds
€ 168,491.92
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2024 | 138471.00 | 138471.00 | 27 |
2025 | 30020.92 | 168491.92 | 33 |
State of progress
Open
Expected start: 18/07/2024
Effective start: 18/07/2024
Expected end: 01/07/2025
Effective end: not available
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI TRICARICO
- Beneficiary
- COMUNE DI TRICARICO
Programming area
- Programme
- ACCORDO COESIONE BASILICATA - FSC ANTICIPAZIONI
- 2021-2027 National Development and Cohesion Fund
- 2021-2027 National Development and Cohesion Fund
- Cohesion funds
- € 500,000.00
- Payments on cohesion funds
- € 168,491.92
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Natura e biodiversita'