CUP: F32E18000020001
PROGETTAZIONE LINEA TRAM F.ICO-STAZIONE BOLOGNA CENTRALE-OSPEDALE MAGGIORE
SUMMARY OF THE PROJECT
LA LINEA PRINCIPALE SI SNODA TRA I CAPOLINEA CAAB E NORMANDIA CON UNA LUNGHEZZA COMPLESSIVA DI 15 KM.
Implementation indicator
Analisi, studi e progettazioni
- Target
- 4 num
- Achieved
- 4 num
Download project
Funding monitored
€ 7,920,521.81
of which cohesion funds
€ 3,992,453.48
Given name | Amount |
---|---|
Development and Cohesion Fund | 3992453.48 |
Municipality | 3928068.33 |
- Economies:
- € 17,931.16
Payments monitored
€ 7,920,521.81
of which cohesion funds
€ 3,992,453.48
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 1159450.83 | 1159450.83 | 14 |
2020 | 2598863.81 | 3758314.64 | 47 |
2021 | 1631580.63 | 5389895.27 | 68 |
2022 | 1465048.00 | 6854943.27 | 86 |
2023 | 1065578.54 | 7920521.81 | 100 |
State of progress
Completed
Expected start: 14/09/2018
Effective start: 14/09/2018
Expected end: 14/11/2022
Effective end: 14/11/2022
Entities
- Planning body
- CITTA METROPOLITANA DI BOLOGNA
- Implementing body
- COMUNE DI BOLOGNA
- Beneficiary
- COMUNE DI BOLOGNA
- Executor
- SYSTRA S.A.
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CITTA' METROPOLITANA DI BOLOGNA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana