CUP: B71B06000560003
MESSA IN SICUREZZA DEL VERSANTE SULLA STRADA PROVINCIALE 149 DAL 3+500 AL KM 5+500 - LOCALIT MARANZA
SUMMARY OF THE PROJECT
MESSA IN SICUREZZA DEL VERSANTE SULLA STRADA PROVINCIALE 149 DAL 3+500 AL KM 5+500 - LOCALIT MARANZA
Implementation indicator
Estensione in lunghezza
- Target
- 2 km
- Achieved
- 2 km
Funding monitored
€ 1,945,269.53
of which cohesion funds
€ 1,157,898.53
Given name | Amount |
---|---|
Development and Cohesion Fund | 1157898.53 |
Province | 787371.00 |
Payments monitored
€ 1,945,269.52
of which cohesion funds
€ 1,157,898.52
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 5875.20 | 5875.20 | 0 |
2008 | 105454.43 | 111329.63 | 5 |
2009 | 0 | 111329.63 | 5 |
2010 | 1607101.39 | 1718431.02 | 88 |
2011 | 214464.16 | 1932895.18 | 99 |
2012 | 0 | 1932895.18 | 99 |
2013 | 7365.12 | 1940260.30 | 99 |
2014 | 5009.22 | 1945269.52 | 99 |
State of progress
Completed
Expected start: 14/09/2009
Effective start: 14/09/2009
Expected end: 12/11/2010
Effective end: 12/11/2010
Entities
- Planning body
- PROVINCIA AUTONOMA DI BOLZANO
- Implementing body
- PROVINCIA AUTONOMA DI BOLZANO
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC P.A. BOLZANO
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale