CUP: B51B07000290003
PROGETTO PER LA REALIZZAZIONE DI OPERE DI MESSA IN SICUREZZA NEL TRATTO TRA I KM 456,800 E KM 459,000 PRESSO COLMA (COMUNE DI RENON)
SUMMARY OF THE PROJECT
PROGETTO PER LA REALIZZAZIONE DI OPERE DI MESSA IN SICUREZZA NEL TRATTO TRA I KM 456,800 E KM 459,000 PRESSO COLMA (COMUNE DI RENON)
Implementation indicator
Estensione in lunghezza
- Target
- 2.80 km
- Achieved
- 2.80 km
Funding monitored
€ 3,001,794.25
of which cohesion funds
€ 735,733.89
Given name | Amount |
---|---|
Development and Cohesion Fund | 735733.89 |
Province | 2266060.36 |
Payments monitored
€ 3,001,794.25
of which cohesion funds
€ 735,733.88
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 64127.74 | 64127.74 | 2 |
2008 | 0 | 64127.74 | 2 |
2009 | 40699.79 | 104827.53 | 3 |
2010 | 1806790.73 | 1911618.26 | 63 |
2011 | 1018456.00 | 2930074.26 | 97 |
2012 | 71719.99 | 3001794.25 | 100 |
State of progress
Completed
Expected start: 22/03/2010
Effective start: 22/03/2010
Expected end: 20/05/2011
Effective end: 20/05/2011
Entities
- Planning body
- PROVINCIA AUTONOMA DI BOLZANO
- Implementing body
- PROVINCIA AUTONOMA DI BOLZANO
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC P.A. BOLZANO
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale