COMPLETAMENTO DEGLI IMPIANTI/REALIZZAZIONE OPERE RISPARMIO ENERGETICO/COMPLETAMENTO - SCUOLA MATERNA ED ELEMENTARE DI BARAGIANO SCALO
SUMMARY OF THE PROJECT
COMPLETAMENTO DEGLI IMPIANTI/REALIZZAZIONE OPERE RISPARMIO ENERGETICO/COMPLETAMENTO - SCUOLA MATERNA ED ELEMENTARE DI BARAGIANO SCALO
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,833 mq
- Achieved
- 1,833 mq
Download project
Funding monitored
€ 315,124.83
of which cohesion funds
€ 315,124.83
Given name | Amount |
---|---|
Development and Cohesion Fund | 315124.83 |
- Economies:
- € 39,475.17
Payments monitored
€ 315,124.83
of which cohesion funds
€ 315,124.83
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 5075.20 | 5075.20 | 1 |
2017 | 207998.22 | 213073.42 | 67 |
2018 | 56774.51 | 269847.93 | 85 |
2019 | 0 | 269847.93 | 85 |
2020 | 9689.50 | 279537.43 | 88 |
2021 | 35587.40 | 315124.83 | 100 |
State of progress
Completed
Expected start: 23/01/2017
Effective start: 23/01/2017
Expected end: 22/12/2020
Effective end: 22/12/2020
Entities
- Planning body
- COMUNE DI BARAGIANO
- Implementing body
- COMUNE DI BARAGIANO
- Beneficiary
- COMUNE DI BARAGIANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative