CUP: I86F05000110009
RISTRUTTURAZIONE E RAZIONALIZZAZIONE DEL SISTEMA DI COLLETTAMENTO REFLUI NEL CENTRO ABITATO E ZONA METAPONTO
SUMMARY OF THE PROJECT
RISTRUTTURAZIONE E RAZIONALIZZAZIONE DEL SISTEMA DI COLLETTAMENTO REFLUI NEL CENTRO ABITATO E ZONA METAPONTO
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 4,101,882.03
of which cohesion funds
€ 4,101,882.03
Given name | Amount |
---|---|
Development and Cohesion Fund | 4101882.03 |
Payments monitored
€ 3,861,001.18
of which cohesion funds
€ 3,861,001.18
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 45057.12 | 45057.12 | 1 |
2010 | 0 | 45057.12 | 1 |
2011 | 144362.01 | 189419.13 | 4 |
2012 | 8918.50 | 198337.63 | 4 |
2013 | 1155047.10 | 1353384.73 | 32 |
2014 | 1668073.69 | 3021458.42 | 73 |
2015 | 203092.06 | 3224550.48 | 78 |
2016 | 636450.70 | 3861001.18 | 94 |
State of progress
Open
Expected start: 05/04/2012
Effective start: 12/04/2012
Expected end: 31/03/2015
Effective end: 30/10/2015
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- ACQUEDOTTO LUCANO SPA
- Beneficiary
- REGIONE BASILICATA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche