CUP: F89G08000110001
COMPLETAMENTO DEL RECUPERO ARCHITETTONICO, STRUTTURALE E FUNZIONALE DEL CASTELLO MEDIOEVALE DI BERNALDA - 3 LOTTO (COMUNE DI BERNALDA - MT)
SUMMARY OF THE PROJECT
COMPLETAMENTO DEL RECUPERO ARCHITETTONICO, STRUTTURALE E FUNZIONALE DEL CASTELLO MEDIOEVALE DI BERNALDA - 3 LOTTO (COMUNE DI BERNALDA - MT)
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,500 mq
- Achieved
- 1,500 mq
Download project
Funding monitored
€ 1,400,000.00
of which cohesion funds
€ 1,400,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1400000.00 |
Payments monitored
€ 1,275,629.65
of which cohesion funds
€ 1,275,629.65
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 6156.56 | 6156.56 | 0 |
2010 | 386064.29 | 392220.85 | 28 |
2011 | 72359.46 | 464580.31 | 33 |
2012 | 90832.00 | 555412.31 | 39 |
2013 | 16667.80 | 572080.11 | 40 |
2014 | 0 | 572080.11 | 40 |
2015 | 1988.47 | 574068.58 | 41 |
2016 | 491571.41 | 1065639.99 | 76 |
2017 | 209989.66 | 1275629.65 | 91 |
State of progress
Open
Expected start: 11/01/2010
Effective start: 11/01/2010
Expected end: 14/12/2017
Effective end: 14/12/2017
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI BERNALDA
- Beneficiary
- REGIONE BASILICATA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio