CUP: B32E18003710002
Lavori di allestimento di un centro fitness per attivita motoria "leggera" nei locali seminterrati e di completamento degli spalti al piano terra della Palestra comunale di Banzi di via Bosco III
SUMMARY OF THE PROJECT
Riqualificazione urbana e territoriale
Implementation indicator
Superficie oggetto di intervento
- Target
- 180 mq
- Achieved
- 180 mq
Download project
Funding monitored
€ 212,163.57
of which cohesion funds
€ 212,163.57
Given name | Amount |
---|---|
Development and Cohesion Fund | 212163.57 |
- Economies:
- € 3,836.43
Payments monitored
€ 212,163.57
of which cohesion funds
€ 212,163.57
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 10150.40 | 10150.40 | 4 |
2020 | 165807.54 | 175957.94 | 82 |
2021 | 7684.71 | 183642.65 | 86 |
2022 | 28520.92 | 212163.57 | 100 |
State of progress
Completed
Expected start: 02/10/2019
Effective start: 02/10/2019
Expected end: 24/01/2022
Effective end: 24/01/2022
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI BANZI
- Beneficiary
- COMUNE DI BANZI
Programming area
- Programme
- PSC REGIONE BASILICATA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 212,163.57
- Payments on cohesion funds
- € 212,163.57
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici