CUP: G23H19000440002
Consolidamento dellarea di valle di Corso Dante
SUMMARY OF THE PROJECT
Mitigazione Rischio Idrogeologico
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 67 m
- Achieved
- 0 m
Download project
Funding monitored
€ 925,000.00
of which cohesion funds
€ 925,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 925000.00 |
Payments monitored
€ 828,552.59
of which cohesion funds
€ 828,552.59
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 50117.60 | 50117.60 | 5 |
2021 | 0 | 50117.60 | 5 |
2022 | 544331.73 | 594449.33 | 64 |
2023 | 234103.26 | 828552.59 | 89 |
State of progress
Open
Expected start: 01/07/2022
Effective start: 01/07/2022
Expected end: 01/09/2023
Effective end: not available
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMMISSARIO STRAORDINARIO DELEGATO PER LA REALIZZAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO PER LA REGIONE BASILICATA
- Beneficiary
- COMMISSARIO STRAORDINARIO DELEGATO PER LA REALIZZAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO PER LA REGIONE BASILICATA
Programming area
- Programme
- PSC REGIONE BASILICATA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 925,000.00
- Payments on cohesion funds
- € 828,552.59
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico