CUP: H72B17000320006
GRANDE ADDUZIONE PRIMARIA - ID 18 - TRAVERSA SARMENTO - SISTEMAZIONE DELL'ALVEO A MONTE DELLA TRAVERSA PER LA CORRETTA REGIMENTAZIONE DEI FLUSSI FLUVIALI VERSO L'OPERA DI PRESA E RIEFFICIENTAMENTO DELLA TRAVERSA PER IL CONTROLLO IN REMOTO DELLE APPARECCHIATURE
SUMMARY OF THE PROJECT
INTERVENTI DI EFFICENTAMENTO AUTOMAZIONE PARATOIE, PULIZIA E RIPROFILATURA DELL'ALVEO A MONTE DELLA TRAVERSA, PULIZIA DELLE VASCHE DI DISSIPAZIONE, RIPRISTINO DELLE SOGLIE AMMALORATE, AMMODERNAMENTO CASA DI GUARDIA E COMPLETAMENTO DEI LAVORI GIA INIZIATI IN SOMMA URGENZA PER LA SISTEMAZIONE DEL CANALE DI SBOCCO NELL'INVASO DI MONTE COTUGNO.
Implementation indicator
Ampliamento di portata
- Target
- 100 mc/s
- Achieved
- 0 mc/s
Download project
Funding monitored
€ 1,630,000.00
of which cohesion funds
€ 1,630,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1630000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 03/09/2021
Effective start: not available
Expected end: 05/11/2021
Effective end: not available
Entities
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche