CUP: H78H17000230006
ID 1 - ADDUTTORE SINNI - RIEFFICIENTAMENTO DELLE APPARECCHIATURE DI REGOLAZIONE E SEZIONAMENTO INSTALLATE SULLE TUBAZIONI DN 2000_1600 IN INGRESSO ALLA TORRE 1V E DN 3000 TORRI 2 E 4 BIS E SULLE DERIVAZIONI IRRIGUE
SUMMARY OF THE PROJECT
INTERVENTO DI RIEFFICIENTAMENTO DELLE APPARECCHIATURE DI REGOLAZIONE E SEZIONAMENTO INSTALLATE SULLE TUBAZIONI DN 2000_1600 IN INGRESSO ALLA TORRE 1V E DN 3000 TORRI 2 E 4 BIS E SULLE DERIVAZIONI IRRIGUE DELL'ADDUTTORE SINNI.
Implementation indicator
Ampliamento di portata
- Target
- 100 mc/s
- Achieved
- 100 mc/s
Download project
Funding monitored
€ 2,150,000.00
of which cohesion funds
€ 2,150,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 2150000.00 |
Payments monitored
€ 1,961,513.69
of which cohesion funds
€ 1,961,513.69
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 118390.01 | 118390.01 | 5 |
2020 | 168225.80 | 286615.81 | 13 |
2021 | 939246.28 | 1225862.09 | 57 |
2022 | 40899.64 | 1266761.73 | 58 |
2023 | 694751.96 | 1961513.69 | 91 |
State of progress
Open
Expected start: 17/02/2021
Effective start: 17/02/2021
Expected end: 28/03/2023
Effective end: 28/03/2023
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA DI ADEGUAMENTO IMPIANTISTICA E O ANTINCENDIO
Theme
Territory
Entities
Programming area
- Programme
- PSC REGIONE BASILICATA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 2,150,000.00
- Payments on cohesion funds
- € 1,961,513.69
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche