CUP: D27H19001920002
LAVORI DI RIPRISTINO E CONSOLIDAMENTO DELLA STRADA COMUNALE DI COLLEGAMENTO COLOBRARO - SINNICA
SUMMARY OF THE PROJECT
LAVORI DI RIPRISTINO E CONSOLIDAMENTO DELLA STRADA COMUNALE DI COLLEGAMENTO COLOBRARO - SINNICA
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 259,235.56
of which cohesion funds
€ 259,235.56
Given name | Amount |
---|---|
Development and Cohesion Fund | 259235.56 |
- Economies:
- € 569.84
Payments monitored
€ 259,235.56
of which cohesion funds
€ 259,235.56
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 924.78 | 924.78 | 0 |
2021 | 172748.32 | 173673.10 | 66 |
2022 | 85562.46 | 259235.56 | 100 |
State of progress
Completed
Expected start: 04/11/2020
Effective start: 09/11/2020
Expected end: 30/11/2021
Effective end: 15/11/2021
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI COLOBRARO
- Beneficiary
- COMUNE DI COLOBRARO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale