CUP: H77H17000630001
CONSOLIDAMENTO E MESSA IN SICUREZZA DELLA S.P. EX SS 7 APPIA SECONDO TRATTO -POTENZA-VAGLIO-PROVINCIA MT
SUMMARY OF THE PROJECT
INTERVENTO DI MESSA IN SICUREZZA DELLA RETE STRADALE REGIONALE ED INFRAREGIONALE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 4 km
- Achieved
- 4 km
Funding monitored
€ 500,000.00
of which cohesion funds
€ 500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 500000.00 |
Payments monitored
€ 338,881.17
of which cohesion funds
€ 338,881.17
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 1593.52 | 1593.52 | 0 |
2020 | 337287.65 | 338881.17 | 67 |
State of progress
Open
Expected start: 01/02/2020
Effective start: 22/01/2020
Expected end: 07/08/2020
Effective end: 20/06/2020
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale