Updated on 30/04/2025
Funding monitored € 440,000.00 of which cohesion funds € 402,600.00
Given name Amount
Development and Cohesion Fund402600.00
Status: other measures37400.00
Payments monitored € 354,507.52 of which cohesion funds € 332,874.38
Year Amount Cumulative amount Percentage on public financing
20126168.426168.421
201322005.5728173.996
201431787.8859961.8713
2015294545.65354507.5280

State of progress

Open
Expected start: 04/09/2014
Effective start: 04/09/2014
Expected end: 06/11/2014
Effective end: 06/11/2014

Type

Theme

  • Environment
  • Altre misure per tutelare l'ambiente e prevenire i rischi

Territory

Entities

Planning body
MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
Implementing body
COMMISSARIO STRAORDINARIO DELEGATO ALL¿ATTUAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO DI CUI ALL¿ACCORDO DI PROGRAMMA TRA IL MINISTERO DELL¿AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE E LA REGIONE PIEMONTE (D.P.C.M. 19 APRILE 2011)
Beneficiary
COMUNE DI ROCCHETTA LIGURE (AL)
Executor
COMUNE DI ROCCHETTA LIGURE (AL)
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

Programme
PROGRAMMA NAZIONALE DI ATTUAZIONE (PNA) FSC RISANAMENTO AMBIENTALE
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 402,600.00
Payments on cohesion funds
€ 332,874.38
Line
Interventi di risanamento ambientale Regione Piemonte
Action
AP per la mitigazione del rischio idrogeologico Regione Piemonte

Other projects in territory