PIANO DI RIORGANIZZAZIONE DELLA MOBILITA
SUMMARY OF THE PROJECT
ELABORAZIONE DI UN PIANO DI RIORGANIZZAZIONE DELLA MOBILITA IN GRADO DI INDICARE, DA UN LATO, IL SISTEMA DI OFFERTA DEI TRASPORTI ESISTENTE, DALLALTRO LATO, LA NECESSITA DI ATTIVARE NUOVI INTERVENTI PER APRIRE IL TERRITORIO DELLAREA INTERNA AL SISTEMA DI TRASPORTO NAZIONALE (NUOVE LINEE DI TPL, MIGLIORAMENTO NEL COLLEGAMENTO AUTOSTRADALE, AEROPORTUALE E FERROVIARIO).
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 2 km
- Achieved
- 1 km
Funding monitored
€ 95,343.12
of which cohesion funds
€ 95,343.12
Given name | Amount |
---|---|
Revolving Fund | 82000.00 |
Another public source | 13343.12 |
Payments monitored
€ 63,343.12
of which cohesion funds
€ 63,343.12
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 12692.62 | 12692.62 | 13 |
2023 | 37987.88 | 50680.50 | 53 |
2024 | 12662.62 | 63343.12 | 66 |
State of progress
Open
Expected start: 08/09/2021
Effective start: 08/09/2021
Expected end: 30/06/2026
Effective end: not available
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- UNIONE MONTANA SPETTABILE REGGENZA DEI SETTE COMUNI
- Beneficiary
- UNIONE MONTANA SPETTABILE REGGENZA DEI SETTE COMUNI
Programming area
- Ordinary resources
- Risorse nazionali ordinarie
- Programme
- STRATEGIA AREE INTERNE REGIONE VENETO SERVIZI
- Internal Area
- Area Interna "Unione Montana Spettabile Reggenza dei sette comuni"
- Scope of action
- MobilitÃÂ