CUP: H89J12000160001
S.P. 12 'Vietrese' - Consolidamento e messa in sicurezza
SUMMARY OF THE PROJECT
S.P. 12 'Vietrese' - Consolidamento e messa in sicurezza
Implementation indicator
Estensione in lunghezza
- Target
- 3 km
- Achieved
- 3 km
Download project
Funding monitored
€ 365,955.07
of which cohesion funds
€ 365,955.07
Given name | Amount |
---|---|
Development and Cohesion Fund | 365955.07 |
Payments monitored
€ 365,955.07
of which cohesion funds
€ 365,955.07
100%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 332507.62 | 332507.62 | 90 |
2017 | 4345.31 | 336852.93 | 92 |
2018 | 29102.14 | 365955.07 | 100 |
State of progress
Completed
Expected start: 12/01/2016
Effective start: 12/10/2015
Expected end: 06/01/2017
Effective end: 09/11/2016
Entities
- Planning body
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
Programming area
- Programme
- PSC REGIONE BASILICATA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 365,955.07
- Payments on cohesion funds
- € 365,955.07
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale