CUP: H49J12000260001
S.P.25 TER 'ARROCCAMENTO GRUMENTINA' - CONSOLIDAMENTO E MESSA IN SICUREZZA
SUMMARY OF THE PROJECT
S.P.25 TER 'ARROCCAMENTO GRUMENTINA' - CONSOLIDAMENTO E MESSA IN SICUREZZA
Implementation indicator
Estensione in lunghezza
- Target
- 5 km
- Achieved
- 5 km
Funding monitored
€ 223,426.58
of which cohesion funds
€ 223,426.58
Given name | Amount |
---|---|
Development and Cohesion Fund | 223426.58 |
Payments monitored
€ 223,426.58
of which cohesion funds
€ 223,426.58
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 15470.71 | 15470.71 | 6 |
2017 | 1078.33 | 16549.04 | 7 |
2018 | 200854.64 | 217403.68 | 97 |
2019 | 6022.90 | 223426.58 | 100 |
State of progress
Completed
Expected start: 13/11/2017
Effective start: 07/11/2017
Expected end: 11/10/2018
Effective end: 16/10/2018
Entities
- Planning body
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI POTENZA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale