CUP: H97H13000420001
S.P. Fondovalle Basentello. Opere di ricostruzione corpo stradale in vari tratti
SUMMARY OF THE PROJECT
S.P. Fondovalle Basentello. Opere di ricostruzione corpo stradale in vari tratti
Implementation indicator
Estensione in lunghezza
- Target
- 12.50 km
- Achieved
- 12.50 km
Download project
Funding monitored
€ 172,848.44
of which cohesion funds
€ 172,848.44
Given name | Amount |
---|---|
Development and Cohesion Fund | 172848.44 |
Payments monitored
€ 172,848.44
of which cohesion funds
€ 172,848.44
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 161328.96 | 161328.96 | 93 |
2017 | 11519.48 | 172848.44 | 100 |
State of progress
Completed
Expected start: 15/04/2016
Effective start: 29/04/2016
Expected end: 04/07/2016
Effective end: 05/08/2016
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- REGIONE BASILICATA
- Beneficiary
- REGIONE BASILICATA
Programming area
- Programme
- PSC REGIONE BASILICATA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 172,848.44
- Payments on cohesion funds
- € 172,848.44
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale