CUP: I27B15000130002
RISTRUTTURAZIONE E REALIZZAZIONE CAMPO SPORTIVO
SUMMARY OF THE PROJECT
RISTRUTTURAZIONE E REALIZZAZIONE CAMPO SPORTIVO
Implementation indicator
Superficie oggetto di intervento
- Target
- 350 mq
- Achieved
- 350 mq
Download project
Funding monitored
€ 99,414.57
of which cohesion funds
€ 99,414.57
Given name | Amount |
---|---|
Development and Cohesion Fund | 99414.57 |
- Economies:
- € 585.43
Payments monitored
€ 99,414.57
of which cohesion funds
€ 99,414.57
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 89999.80 | 89999.80 | 90 |
2018 | 9414.77 | 99414.57 | 100 |
State of progress
Completed
Expected start: 18/07/2016
Effective start: 18/07/2016
Expected end: 31/01/2017
Effective end: 31/01/2017
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI RAIANO
- Beneficiary
- COMUNE DI RAIANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e Paesaggio