CUP: C94B13001500000
CONSOLIDAMENTO E MIGLIORAMENTO SISMICO DEL FABBRICATO SITO NE COMUNE DI FOSSACESIA IN VIA T. NATALE
SUMMARY OF THE PROJECT
CONSOLIDAMENTO E MIGLIORAMENTO SISMICO DEL FABBRICATO SITO NE COMUNE DI FOSSACESIA IN VIA T. NATALE
Implementation indicator
Volume oggetto di intervento
- Target
- 3,130 mc
- Achieved
- 3,130 mc
Funding monitored
€ 369,539.09
of which cohesion funds
€ 353,496.83
Given name | Amount |
---|---|
Development and Cohesion Fund | 353496.83 |
Another public source | 16042.26 |
- Economies:
- € 82,668.67
Payments monitored
€ 353,496.83
of which cohesion funds
€ 340,583.07
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 12913.76 | 12913.76 | 3 |
2016 | 0 | 12913.76 | 3 |
2017 | 0 | 12913.76 | 3 |
2018 | 356625.33 | 369539.09 | 100 |
2019 | 0 | 369539.09 | 100 |
2020 | 0 | 369539.09 | 100 |
2021 | 0 | 369539.09 | 100 |
2022 | 0 | 369539.09 | 100 |
2023 | 12913.76 | 382452.85 | 103 |
2024 | -28956.02 | 353496.83 | 95 |
State of progress
Completed
Expected start: 19/01/2020
Effective start: 11/07/2016
Expected end: 19/01/2022
Effective end: 31/12/2021
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- ATER DI LANCIANO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici