REALIZZAZIONE IMPIANTO SPORTIVO - REALIZZAZIONE TORRI FARO ST. ADR. - C.NE DI PESCARA
SUMMARY OF THE PROJECT
REALIZZAZIONE IMPIANTO SPORTIVO - REALIZZAZIONE TORRI FARO ST. ADR. - C.NE DI PESCARA
Download project
Funding monitored
€ 490,733.81
of which cohesion funds
€ 122,683.45
Given name | Amount |
---|---|
Development and Cohesion Fund | 122683.45 |
Municipality | 368050.36 |
- Economies:
- € 196,266.19
Payments monitored
€ 490,733.81
of which cohesion funds
€ 122,683.44
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 14834.01 | 14834.01 | 3 |
2015 | 373374.02 | 388208.03 | 79 |
2016 | 102611.78 | 490819.81 | 100 |
2017 | -86.00 | 490733.81 | 100 |
State of progress
Completed
Expected start: 04/09/2014
Effective start: 04/09/2014
Expected end: 18/12/2014
Effective end: 18/12/2014
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI PESCARA
- Beneficiary
- REGIONE ABRUZZO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 122,683.45
- Payments on cohesion funds
- € 122,683.44
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e Paesaggio