CUP: C31B14000140007
PROGETTO ESECUTIVO DI ADEGUAMENTO DELL'IMPIANTO DI DEPURAZIONE SITO NEL COMUNE DI CASTIGLIONE MESSER RAIMONDO LOC. COSTE
SUMMARY OF THE PROJECT
PROGETTO ESECUTIVO DI ADEGUAMENTO DELL'IMPIANTO DI DEPURAZIONE SITO NEL COMUNE DI CASTIGLIONE MESSER RAIMONDO LOC. COSTE
Download project
Funding monitored
€ 171,285.78
of which cohesion funds
€ 147,970.44
Given name | Amount |
---|---|
Development and Cohesion Fund | 147970.44 |
Another public source | 23315.34 |
- Economies:
- € 33,357.85
Payments monitored
€ 147,970.44
of which cohesion funds
€ 147,970.44
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 149217.00 | 149217.00 | 87 |
2020 | 0 | 149217.00 | 87 |
2021 | 0 | 149217.00 | 87 |
2022 | 0 | 149217.00 | 87 |
2023 | 0 | 149217.00 | 87 |
2024 | -1246.56 | 147970.44 | 86 |
State of progress
Open
Expected start: 15/03/2019
Effective start: 15/03/2019
Expected end: 31/12/2022
Effective end: 15/11/2022
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- AZIENDA COMPRENSORIALE ACQUEDOTTISTICA SPA IN HOUSE PROVIDING
- Beneficiary
- AMBITO TERRITORIALE OTTIMALE N4 DEL PESCARESE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche