CUP: B17H14001150001
REALIZZAZIONE NUOVI SISTEMI DI DEPURAZIONE DEL SISTEMA FOGNARIO DEL COMPARTO ZONA SUBEQUANA E PRECISAMENTE DELLE CRITICIT RISCONTRATE NEI COMUNI DI ACCIANO, E GAGNANO ALTO (E FRAZIONI: BEFFI - ROCCAPRETURO - S. LORENZO - SUCCIANO - CAMPANA (CASTELLO, COLLE, CORBELLINO, FRASCARA, VALLECUPA) - PEDICCIANO - RIPA FAGNANO E TERMINE)
SUMMARY OF THE PROJECT
REALIZZAZIONE NUOVI SISTEMI DI DEPURAZIONE DEL SISTEMA FOGNARIO DEL COMPARTO ZONA SUBEQUANA E PRECISAMENTE DELLE CRITICIT RISCONTRATE NEI COMUNI DI ACCIANO, E GAGNANO ALTO (E FRAZIONI: BEFFI - ROCCAPRETURO - S. LORENZO - SUCCIANO - CAMPANA (CASTELLO, COLLE, CORBELLINO, FRASCARA, VALLECUPA) - PEDICCIANO - RIPA FAGNANO E TERMINE)
Download project
Funding monitored
€ 1,492,211.61
of which cohesion funds
€ 1,232,541.60
Given name | Amount |
---|---|
Development and Cohesion Fund | 1232541.60 |
Another public source | 259670.01 |
- Economies:
- € 433,823.69
Payments monitored
€ 1,088,338.95
of which cohesion funds
€ 828,668.94
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 4355.00 | 4355.00 | 0 |
2015 | 0 | 4355.00 | 0 |
2016 | 253749.24 | 258104.24 | 17 |
2017 | 785489.79 | 1043594.03 | 69 |
2018 | 484257.52 | 1527851.55 | 102 |
2019 | 131178.71 | 1659030.26 | 111 |
2020 | 1238.94 | 1660269.20 | 111 |
2021 | 51923.06 | 1712192.26 | 114 |
2022 | 8179.15 | 1720371.41 | 115 |
2023 | -151903.24 | 1568468.17 | 105 |
2024 | -480129.22 | 1088338.95 | 72 |
State of progress
Open
Expected start: 04/07/2016
Effective start: 22/08/2016
Expected end: 01/11/2020
Effective end: 09/08/2020
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- GRAN SASSO ACQUA SPA
- Beneficiary
- ENTE AMBITO TERRITORIALE AQUILANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche