CUP: J86J04000020009
AMPLIAMENTO IMPIANTO DI DEPURAZIONE DI PIZZOLI E COLLETTORE FOGNARIO A SERVIZIO DEL COMUNE DI PIZZOLI (FRAZ. BARETE, TEORA), CAGNANO AMITERNO (FRAZ. SAN GIOVANNI, SAN COSIMO), MONTEREALE (FRAZ. MARANA)
SUMMARY OF THE PROJECT
AMPLIAMENTO IMPIANTO DI DEPURAZIONE DI PIZZOLI E COLLETTORE FOGNARIO A SERVIZIO DEL COMUNE DI PIZZOLI (FRAZ. BARETE, TEORA), CAGNANO AMITERNO (FRAZ. SAN GIOVANNI, SAN COSIMO), MONTEREALE (FRAZ. MARANA)
Implementation indicator
Capacita' trattamento reflui oggetto di intervento
- Target
- 0.03 mc/s
- Achieved
- 0.03 mc/s
Download project
Funding monitored
€ 5,420,200.00
of which cohesion funds
€ 1,600,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1600000.00 |
Another public source | 3820200.00 |
Payments monitored
€ 5,420,200.00
of which cohesion funds
€ 1,600,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 2102438.91 | 2102438.91 | 38 |
2010 | 2645681.24 | 4748120.15 | 87 |
2011 | 136065.60 | 4884185.75 | 90 |
2012 | 0 | 4884185.75 | 90 |
2013 | 0 | 4884185.75 | 90 |
2014 | 0 | 4884185.75 | 90 |
2015 | 0 | 4884185.75 | 90 |
2016 | 0 | 4884185.75 | 90 |
2017 | 0 | 4884185.75 | 90 |
2018 | 0 | 4884185.75 | 90 |
2019 | 536014.25 | 5420200.00 | 100 |
State of progress
Completed
Expected start: 05/06/2009
Effective start: 05/06/2009
Expected end: 14/07/2010
Effective end: 14/07/2010
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- REGIONE ABRUZZO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,600,000.00
- Payments on cohesion funds
- € 1,600,000.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
COMUNE DI CAGNANO AMITERNO | € 12,000 |
Same type of investment
INFRASTRUTTURE ZONA ARTIGIANALE | € 204,056 |