CUP: G88H03000020006
Realizzazione nuovo impianto di depurazione e collettori fognari
SUMMARY OF THE PROJECT
Realizzazione nuovo impianto di depurazione e collettori fognari
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 774,685.35
of which cohesion funds
€ 464,811.21
Given name | Amount |
---|---|
Development and Cohesion Fund | 464811.21 |
Another public source | 309874.14 |
Payments monitored
€ 411,918.37
of which cohesion funds
€ 411,918.37
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 183356.24 | 183356.24 | 23 |
2009 | 160378.09 | 343734.33 | 44 |
2010 | 8000.06 | 351734.39 | 45 |
2011 | 0 | 351734.39 | 45 |
2012 | 0 | 351734.39 | 45 |
2013 | 0 | 351734.39 | 45 |
2014 | 0 | 351734.39 | 45 |
2015 | 0 | 351734.39 | 45 |
2016 | 60183.98 | 411918.37 | 53 |
State of progress
Open
Expected start: 16/12/2004
Effective start: 16/12/2004
Expected end: 15/07/2024
Effective end: not available
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- ENTE D'AMBITO TERRITORIALE - MARSICANO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 464,811.21
- Payments on cohesion funds
- € 411,918.37
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
Realizzazione di strutture e infrastrutture per l'incentivazione delle attivit produttive | € 89,938 |
Borse Lavoro lavoratori svantaggiati Regolamento (CE) n. 800/2008 - GIGLI RENZA | € 3,255 |
Same type of investment
banda Ultralarga nelle aree bianche del territorio della Regione Abruzzo con FONDI FSC | € 22,011,575 |
Realizzazione di strutture e infrastrutture per l'incentivazione delle attivit produttive | € 89,938 |