CUP: H38F01000020006
Adeguamento e Potenziamento dell'Impianto di Scerne di Pineto
SUMMARY OF THE PROJECT
Adeguamento e Potenziamento dell'Impianto di Scerne di Pineto
Implementation indicator
Capacita' trattamento reflui oggetto di intervento
- Target
- 0.06 mc/s
- Achieved
- 0.06 mc/s
Download project
Funding monitored
€ 1,971,354.10
of which cohesion funds
€ 847,682.26
Given name | Amount |
---|---|
Development and Cohesion Fund | 847682.26 |
Another public source | 1123671.84 |
- Economies:
- € 390,645.90
Payments monitored
€ 1,971,354.10
of which cohesion funds
€ 847,682.26
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 439764.62 | 439764.62 | 22 |
2006 | 407917.64 | 847682.26 | 42 |
2007 | 0 | 847682.26 | 42 |
2008 | 0 | 847682.26 | 42 |
2009 | 0 | 847682.26 | 42 |
2010 | 0 | 847682.26 | 42 |
2011 | 0 | 847682.26 | 42 |
2012 | 0 | 847682.26 | 42 |
2013 | 0 | 847682.26 | 42 |
2014 | 0 | 847682.26 | 42 |
2015 | 0 | 847682.26 | 42 |
2016 | 0 | 847682.26 | 42 |
2017 | 0 | 847682.26 | 42 |
2018 | 0 | 847682.26 | 42 |
2019 | 0 | 847682.26 | 42 |
2020 | 0 | 847682.26 | 42 |
2021 | 0 | 847682.26 | 42 |
2022 | 0 | 847682.26 | 42 |
2023 | 0 | 847682.26 | 42 |
2024 | 1123671.84 | 1971354.10 | 100 |
State of progress
Completed
Expected start: 29/12/2004
Effective start: 29/12/2004
Expected end: 15/01/2006
Effective end: 15/01/2006
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- REGIONE ABRUZZO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 847,682.26
- Payments on cohesion funds
- € 847,682.26
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche