CUP: D65F06000060005
Lavori di completamento fognatura Pescara Porta Nuova e adeguamento impianto dep. 2^ lotto, 1^ stralcio
SUMMARY OF THE PROJECT
Lavori di completamento fognatura Pescara Porta Nuova e adeguamento impianto dep. 2^ lotto, 1^ stralcio
Implementation indicator
Portata media equivalente
- Target
- 0.03 mc/s
- Achieved
- 0.03 mc/s
Download project
Funding monitored
€ 3,890,838.07
of which cohesion funds
€ 2,334,502.84
Given name | Amount |
---|---|
Development and Cohesion Fund | 2334502.84 |
Another public source | 1556335.23 |
- Economies:
- € 757,274.03
Payments monitored
€ 3,890,838.07
of which cohesion funds
€ 2,334,502.84
100%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 214720.57 | 214720.57 | 5 |
2007 | 1200.00 | 215920.57 | 5 |
2008 | 1180290.88 | 1396211.45 | 35 |
2009 | 770484.84 | 2166696.29 | 55 |
2010 | 1513.53 | 2168209.82 | 55 |
2011 | 77175.42 | 2245385.24 | 57 |
2012 | 71155.60 | 2316540.84 | 59 |
2013 | 17962.00 | 2334502.84 | 59 |
2014 | 0 | 2334502.84 | 59 |
2015 | 0 | 2334502.84 | 59 |
2016 | 0 | 2334502.84 | 59 |
2017 | 0 | 2334502.84 | 59 |
2018 | 0 | 2334502.84 | 59 |
2019 | 0 | 2334502.84 | 59 |
2020 | 0 | 2334502.84 | 59 |
2021 | 0 | 2334502.84 | 59 |
2022 | 0 | 2334502.84 | 59 |
2023 | 0 | 2334502.84 | 59 |
2024 | 1556335.23 | 3890838.07 | 100 |
State of progress
Completed
Expected start: 16/01/2007
Effective start: 16/01/2007
Expected end: 30/05/2009
Effective end: 30/05/2009
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- REGIONE ABRUZZO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 2,334,502.84
- Payments on cohesion funds
- € 2,334,502.84
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche