CUP: I78F04000000005
Impianti ricadenti negli obblighi di cui al D.L.vo 152/99. Potenziamento impianto di depurazione di Sulmona (Ponte la Torre) e collettamento Comuni di Introdacqua, Pettorano e Bugnara (parte bassa)
SUMMARY OF THE PROJECT
Impianti ricadenti negli obblighi di cui al D.L.vo 152/99. Potenziamento impianto di depurazione di Sulmona (Ponte la Torre) e collettamento Comuni di Introdacqua, Pettorano e Bugnara (parte bassa)
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 2,541,418.31
of which cohesion funds
€ 1,778,993.24
Given name | Amount |
---|---|
Development and Cohesion Fund | 1778993.24 |
Another public source | 762425.07 |
- Economies:
- € 494,315.34
Payments monitored
€ 2,541,418.31
of which cohesion funds
€ 1,778,993.24
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 157233.70 | 157233.70 | 6 |
2007 | 0 | 157233.70 | 6 |
2008 | 134254.53 | 291488.23 | 11 |
2009 | 0 | 291488.23 | 11 |
2010 | 1487505.01 | 1778993.24 | 70 |
2011 | 0 | 1778993.24 | 70 |
2012 | 0 | 1778993.24 | 70 |
2013 | 0 | 1778993.24 | 70 |
2014 | 0 | 1778993.24 | 70 |
2015 | 0 | 1778993.24 | 70 |
2016 | 0 | 1778993.24 | 70 |
2017 | 0 | 1778993.24 | 70 |
2018 | 0 | 1778993.24 | 70 |
2019 | 0 | 1778993.24 | 70 |
2020 | 0 | 1778993.24 | 70 |
2021 | 0 | 1778993.24 | 70 |
2022 | 0 | 1778993.24 | 70 |
2023 | 0 | 1778993.24 | 70 |
2024 | 762425.07 | 2541418.31 | 100 |
State of progress
Completed
Expected start: 02/10/2006
Effective start: 02/10/2006
Expected end: 18/05/2009
Effective end: 18/05/2009
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- REGIONE ABRUZZO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 1,778,993.24
- Payments on cohesion funds
- € 1,778,993.24
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche