CUP: I99J05000100006
Adeguamento e messa in sicurezza dell'asse viario 'Pretoro Passolanciano'
SUMMARY OF THE PROJECT
Adeguamento e messa in sicurezza dell'asse viario 'Pretoro Passolanciano'
Implementation indicator
Estensione in lunghezza
- Target
- 7.20 km
- Achieved
- 7.20 km
Download project
Funding monitored
€ 3,347,137.90
of which cohesion funds
€ 3,347,137.90
Given name | Amount |
---|---|
Development and Cohesion Fund | 3347137.90 |
- Economies:
- € 303,426.02
Payments monitored
€ 3,089,341.06
of which cohesion funds
€ 3,089,341.06
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 132788.45 | 132788.45 | 3 |
2007 | 604152.63 | 736941.08 | 22 |
2008 | 591565.08 | 1328506.16 | 39 |
2009 | 586871.68 | 1915377.84 | 57 |
2010 | 861516.49 | 2776894.33 | 82 |
2011 | 8326.60 | 2785220.93 | 83 |
2012 | 28179.63 | 2813400.56 | 84 |
2013 | 220000.00 | 3033400.56 | 90 |
2014 | 55940.50 | 3089341.06 | 92 |
State of progress
Open
Expected start: 20/04/2006
Effective start: 20/04/2006
Expected end: 08/05/2014
Effective end: 08/05/2014
Entities
- Planning body
- COMUNE DI PRETORO
- Implementing body
- COMUNE DI PRETORO
- Beneficiary
- COMUNE DI PRETORO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 3,347,137.90
- Payments on cohesion funds
- € 3,089,341.06
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto Stradale
Other projects in territory
Same theme
Same type of investment
COMUNE DI PRETORO | € 49,204 |