CUP: E73B07000000002
Progetto di consolidamento del dissesto idrogeologico in frazione Mutignano del Comune di Pineto (TE)
SUMMARY OF THE PROJECT
Progetto di consolidamento del dissesto idrogeologico in frazione Mutignano del Comune di Pineto (TE)
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,300 mq
- Achieved
- 1,300 mq
Download project
Funding monitored
€ 366,098.38
of which cohesion funds
€ 366,098.38
Given name | Amount |
---|---|
Development and Cohesion Fund | 366098.38 |
Payments monitored
€ 366,098.38
of which cohesion funds
€ 366,098.38
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 36371.74 | 36371.74 | 9 |
2009 | 282418.27 | 318790.01 | 87 |
2010 | 0 | 318790.01 | 87 |
2011 | 47308.37 | 366098.38 | 100 |
State of progress
Completed
Expected start: 29/12/2008
Effective start: 29/12/2008
Expected end: 22/12/2010
Effective end: 22/12/2010
Entities
- Planning body
- COMUNE DI PINETO
- Implementing body
- COMUNE DI PINETO
- Beneficiary
- COMUNE DI PINETO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 366,098.38
- Payments on cohesion funds
- € 366,098.38
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico