CUP: E56J07000030001
IMPIANTO DI TRATTAMENO CHIMICO FISICO OPERE DI COMPLETAMENTO
SUMMARY OF THE PROJECT
IMPIANTO DI TRATTAMENO CHIMICO FISICO OPERE DI COMPLETAMENTO
Implementation indicator
Superficie oggetto di intervento
- Target
- 9,000 mq
- Achieved
- 9,000 mq
Download project
Funding monitored
€ 206,261.00
of which cohesion funds
€ 206,261.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 206261.00 |
Payments monitored
€ 206,261.00
of which cohesion funds
€ 206,261.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 150.00 | 150.00 | 0 |
2008 | 150.00 | 300.00 | 0 |
2009 | 194087.42 | 194387.42 | 94 |
2010 | 11873.58 | 206261.00 | 100 |
State of progress
Completed
Expected start: 09/02/2009
Effective start: 09/02/2009
Expected end: 07/08/2009
Effective end: 07/08/2009
Entities
- Planning body
- REGIONE ABRUZZO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e Servizi