CUP: G59E04000040001
LAVORI PER LA REALIZZAZIONE DI INFRASTRUTTURE A COMPLETAMENTO DI AREE ATTREZZATE PER INSEDIAMENTI PRODUTTIVI
SUMMARY OF THE PROJECT
LAVORI PER LA REALIZZAZIONE DI INFRASTRUTTURE A COMPLETAMENTO DI AREE ATTREZZATE PER INSEDIAMENTI PRODUTTIVI
Implementation indicator
Superficie oggetto di intervento
- Target
- 3,543 mq
- Achieved
- 3,543 mq
Download project
Funding monitored
€ 347,885.36
of which cohesion funds
€ 347,885.36
Given name | Amount |
---|---|
Development and Cohesion Fund | 347885.36 |
- Economies:
- € 45,389.08
Payments monitored
€ 347,885.36
of which cohesion funds
€ 347,885.36
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 71400.27 | 71400.27 | 20 |
2007 | 175529.35 | 246929.62 | 70 |
2008 | 100955.74 | 347885.36 | 100 |
State of progress
Completed
Expected start: 05/04/2006
Effective start: 05/04/2006
Expected end: 10/09/2008
Effective end: 10/09/2008
Entities
- Planning body
- COMUNE DI CASOLI
- Implementing body
- COMUNE DI CASOLI
- Beneficiary
- COMUNE DI CASOLI
Programming area
- Programme
- PSC REGIONE ABRUZZO
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 347,885.36
- Payments on cohesion funds
- € 347,885.36
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e Servizi