CUP: I41B15000110006
PISTA CICLABILE
SUMMARY OF THE PROJECT
PISTA CICLABILE
Implementation indicator
Estensione in lunghezza
- Target
- 2.62 km
- Achieved
- 2.62 km
Download project
Funding monitored
€ 786,602.25
of which cohesion funds
€ 552,418.55
Given name | Amount |
---|---|
Development and Cohesion Fund | 552418.55 |
Municipality | 234183.70 |
- Economies:
- € 48,397.75
Payments monitored
€ 786,602.25
of which cohesion funds
€ 552,418.53
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 1491.12 | 1491.12 | 0 |
2016 | 262743.27 | 264234.39 | 33 |
2017 | 287943.07 | 552177.46 | 70 |
2018 | 234424.79 | 786602.25 | 100 |
State of progress
Completed
Expected start: 15/05/2016
Effective start: 16/05/2016
Expected end: 15/10/2017
Effective end: 27/09/2017
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI LANCIANO
- Beneficiary
- COMUNE DI LANCIANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e Paesaggio