CUP: C92J12000280001
INTERVENTO 2 - FIUME NORA - OPERE DI RAFFORZAMENTO E DI DIFESA SPONDALE.
SUMMARY OF THE PROJECT
INTERVENTO 2 - FIUME NORA - OPERE DI RAFFORZAMENTO E DI DIFESA SPONDALE.
Implementation indicator
Estensione in lunghezza
- Target
- 1.30 km
- Achieved
- 1.30 km
Funding monitored
€ 260,000.00
of which cohesion funds
€ 260,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 260000.00 |
- Economies:
- € 40,000.00
Payments monitored
€ 199,028.96
of which cohesion funds
€ 199,028.96
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 10628.46 | 10628.46 | 4 |
2015 | 870.25 | 11498.71 | 4 |
2016 | 870.25 | 12368.96 | 4 |
2017 | 164700.00 | 177068.96 | 68 |
2018 | 21960.00 | 199028.96 | 76 |
State of progress
Open
Expected start: 01/12/2014
Effective start: 02/09/2015
Expected end: 30/01/2023
Effective end: not available
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- REGIONE ABRUZZO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico