CUP: C22J12000180001
Intervento 2 - Fiume Aventino Realizzazione di opere di sistemazione e protezione spondale.
SUMMARY OF THE PROJECT
Intervento 2 - Fiume Aventino Realizzazione di opere di sistemazione e protezione spondale.
Implementation indicator
Estensione in lunghezza
- Target
- 4 km
- Achieved
- 4 km
Download project
Funding monitored
€ 356,965.59
of which cohesion funds
€ 356,965.59
Given name | Amount |
---|---|
Development and Cohesion Fund | 356965.59 |
- Economies:
- € 43,034.41
Payments monitored
€ 356,965.59
of which cohesion funds
€ 356,965.59
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 15865.08 | 15865.08 | 4 |
2015 | 229931.89 | 245796.97 | 68 |
2016 | 108302.92 | 354099.89 | 99 |
2017 | 0 | 354099.89 | 99 |
2018 | 0 | 354099.89 | 99 |
2019 | 0 | 354099.89 | 99 |
2020 | 2865.70 | 356965.59 | 100 |
State of progress
Completed
Expected start: 25/11/2014
Effective start: 25/11/2014
Expected end: 15/10/2015
Effective end: 15/10/2015
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- REGIONE ABRUZZO
- Beneficiary
- REGIONE ABRUZZO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 356,965.59
- Payments on cohesion funds
- € 356,965.59
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico