CUP: J29C13000020002
INTERVENTI DI NUOVA REALIZZAZIONE E RIPRISTINO DI IMPIANTI A FUNE (SEGGIOVIE) NEL COMPRENSORIO DI PESCASSEROLI
SUMMARY OF THE PROJECT
INTERVENTI DI NUOVA REALIZZAZIONE E RIPRISTINO DI IMPIANTI A FUNE (SEGGIOVIE) NEL COMPRENSORIO DI PESCASSEROLI
Implementation indicator
Estensione in lunghezza
- Target
- 1.50 km
- Achieved
- 1.50 km
Download project
Funding monitored
€ 2,098,379.97
of which cohesion funds
€ 2,098,379.97
Given name | Amount |
---|---|
Development and Cohesion Fund | 2098379.97 |
Payments monitored
€ 2,098,379.97
of which cohesion funds
€ 2,098,379.97
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 861038.39 | 861038.39 | 41 |
2014 | 825292.42 | 1686330.81 | 80 |
2015 | 412049.16 | 2098379.97 | 100 |
State of progress
Completed
Expected start: 08/08/2013
Effective start: 08/08/2013
Expected end: 07/12/2013
Effective end: 16/12/2013
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI PESCASSEROLI
- Beneficiary
- REGIONE ABRUZZO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 2,098,379.97
- Payments on cohesion funds
- € 2,098,379.97
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana