CUP: G47H20000150002
FONTECCHIO - MESSA IN SICUREZZA STRADE COMUNALI - MURO DI CONTENIMENTO VIA PER SAN PIO - STRADA PER LE PAGLIARE - VIA PER L'ACQUA DEI FRATI
SUMMARY OF THE PROJECT
FONTECCHIO - MESSA IN SICUREZZA STRADE COMUNALI - MURO DI CONTENIMENTO VIA PER SAN PIO - STRADA PER LE PAGLIARE - VIA PER L'ACQUA DEI FRATI
Implementation indicator
Numero di progetti destinati alle pubbliche amministrazioni o ai servizi pubblici a livello nazionale, regionale o locale
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 50,376.44
of which cohesion funds
€ 50,376.44
Given name | Amount |
---|---|
Development and Cohesion Fund | 50376.44 |
- Economies:
- € 1,423.56
Payments monitored
€ 50,376.44
of which cohesion funds
€ 50,376.44
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 49903.88 | 49903.88 | 99 |
2022 | 472.56 | 50376.44 | 100 |
State of progress
Completed
Expected start: 30/08/2020
Effective start: 09/09/2020
Expected end: 30/10/2020
Effective end: 15/12/2020
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI FONTECCHIO
- Beneficiary
- COMUNE DI FONTECCHIO
Programming area
- Programme
- PSC REGIONE ABRUZZO
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,376.44
- Payments on cohesion funds
- € 50,376.44
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto Stradale