CUP: I67H16000620001
Intervento di messa in sicurezza della struttura viaria strada Val Fino - connessione costa teramana-parco del Gran Sasso
SUMMARY OF THE PROJECT
Intervento di messa in sicurezza della struttura viaria strada Val Fino - connessione costa teramana-parco del Gran Sasso
Implementation indicator
Progetti per la fruizione integrata e la promozione
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 9,278,288.19
of which cohesion funds
€ 9,278,288.19
Given name | Amount |
---|---|
Development and Cohesion Fund | 9278288.19 |
Payments monitored
€ 6,169,670.96
of which cohesion funds
€ 6,150,366.96
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 18973.37 | 18973.37 | 0 |
2018 | 45920.60 | 64893.97 | 0 |
2019 | 212554.90 | 277448.87 | 2 |
2020 | 133516.67 | 410965.54 | 4 |
2021 | 33634.37 | 444599.91 | 4 |
2022 | 3638672.14 | 4083272.05 | 44 |
2023 | 1915225.53 | 5998497.58 | 64 |
2024 | 171173.38 | 6169670.96 | 66 |
State of progress
Open
Expected start: 01/03/2021
Effective start: 31/03/2021
Expected end: 31/01/2024
Effective end: 16/01/2024
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI CASTILENTI
- Beneficiary
- COMUNE DI CASTILENTI
- Executor
- COMUNE DI CASTILENTI
Programming area
- Programme
- PSC REGIONE ABRUZZO
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 9,278,288.19
- Payments on cohesion funds
- € 6,150,366.96
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario