CUP: B57B17000180002
REALIZZAZIONE COLLETTORI FOGNARI IN COMUNE DI CASTEL DEL MONTE
SUMMARY OF THE PROJECT
REALIZZAZIONE COLLETTORI FOGNARI IN COMUNE DI CASTEL DEL MONTE
Implementation indicator
Progetti per la fruizione integrata e la promozione
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 216,589.80
of which cohesion funds
€ 173,271.84
Given name | Amount |
---|---|
Development and Cohesion Fund | 173271.84 |
Municipality | 43317.96 |
- Economies:
- € 50,341.76
Payments monitored
€ 216,589.80
of which cohesion funds
€ 173,271.84
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 138804.41 | 138804.41 | 64 |
2021 | 79794.57 | 218598.98 | 100 |
2022 | 0 | 218598.98 | 100 |
2023 | 0 | 218598.98 | 100 |
2024 | -2009.18 | 216589.80 | 100 |
State of progress
Completed
Expected start: 02/03/2020
Effective start: 02/03/2020
Expected end: 01/11/2020
Effective end: 21/10/2020
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI CASTEL DEL MONTE
- Beneficiary
- COMUNE DI CASTEL DEL MONTE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche