CUP: B76J13000400009
PRODUZIONE DI ENERGIA RINNOVABILE E RISTRUTTURAZIONE E SOSTITUZIONE IMPIANTI GENERALI ELETTRICI TERMICI E RISCALDAMENTO
Funding monitored
€ 444,140.58
of which cohesion funds
€ 444,140.58
Given name | Amount |
---|---|
Revolving Fund (Cohesion Action Plan) | 444140.58 |
Payments monitored
€ 444,140.58
of which cohesion funds
€ 444,140.58
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 3569.32 | 3569.32 | 0 |
2016 | 386556.27 | 390125.59 | 87 |
2017 | 54014.99 | 444140.58 | 100 |
State of progress
Completed
Expected start: 10/08/2015
Effective start: 10/08/2015
Expected end: 10/08/2015
Effective end: 10/08/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Administrative capacity
- Progetti integrati per la rigenerazione urbana e rurale
Territory
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- COMUNE DI CASAL VELINO
- Beneficiary
- COMUNE DI CASAL VELINO
- Priority QSN
- Reti e collegamenti per la mobilità
- General objective QSN
- Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
- Specific objective QSN
- Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili
Programming area
- 2007-2013 Cohesion Action Plan
- 2007-2013 Cohesion Action Plan
- Programme
- PROGRAMMA PAC CAMPANIA
- Line
- Salvaguardia
- Action
- Salvaguardia POR FESR 2007/2013