This project is eliminated from views and totals because it will be deactivated due to migration in the Development and Cohesion Plan.
Updated on 31/12/2022
Funding monitored € 65,000,000.00 of which cohesion funds € 0.00
Given name Amount
Status: other measures65000000.00
Payments monitored € 63,254,341.71 of which cohesion funds € 0.00
Year Amount Cumulative amount Percentage on public financing
2010413100.00413100.000
2011842400.001255500.001
201270463.411325963.412
2013657957.761983921.173
20149590276.7311574197.9017
201515521468.4127095666.3141
201612972384.5740068050.8861
20176059677.5146127728.3970
201810629476.7356757205.1287
20194713270.8161470475.9394
20201725704.8563196180.7897
202110554.5463206735.3297
202247606.3963254341.7197

State of progress

Settled
Expected start: 02/01/2015
Effective start: 25/02/2015
Expected end: 30/03/2023
Effective end: not available

Type

Theme

Territory

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
RETE FERROVIARIA ITALIANA SPA
Beneficiary
REGIONE PUGLIA
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili

Programming area

Programme
PROGRAMMA ATTUATIVO SPECIALE FSC DIRETTRICI FERROVIARIE
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 0.00
Payments on cohesion funds
€ 0.00
Line
Direttrice ferroviaria Napoli Bari Lecce Taranto
Action
Direttrice ferroviaria Napoli Bari Lecce Taranto altre opere

Other projects in territory