CUP: B45F10000050003
ASP AGRIGENTO - INTERVENTI LINEA 2.2
Download project
Funding monitored
€ 3,336,582.22
of which cohesion funds
€ 3,336,582.22
Given name | Amount |
---|---|
European Union | 2502436.66 |
Revolving Fund (National co-financing) | 834145.56 |
Payments monitored
€ 3,336,582.22
of which cohesion funds
€ 3,336,582.22
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 730043.62 | 730043.62 | 21 |
2014 | 625751.67 | 1355795.29 | 40 |
2015 | 1301934.38 | 2657729.67 | 79 |
2016 | 678852.55 | 3336582.22 | 100 |
State of progress
Completed
Expected start: 01/07/2012
Effective start: 22/05/2012
Expected end: 30/11/2015
Effective end: 30/11/2015
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- AZIENDA SANITARIA PROVINCIALE DI AGRIGENTO
- Beneficiary
- AZIENDA SANITARIA PROVINCIALE DI AGRIGENTO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- IROP CONV ERDF RENEWABLE ENERGY AND ENERGY CONSERVATION
- Axis
- Asse II Efficienza energetica ed ottimizzazione del sistema
- Operational objective
- Sperimentare e realizzare forme avanzate di interventi di efficientamento energetico su edifici e utenze pubbliche.