CUP: H64E10000270001
INSCT - G. PASCALE DI NAPOLI - INTERVENTI LINEA 2.2
Download project
Funding monitored
€ 4,616,757.22
of which cohesion funds
€ 4,605,907.50
Given name | Amount |
---|---|
European Union | 3454430.62 |
Revolving Fund (National co-financing) | 1151476.88 |
Another public source | 10849.72 |
Payments monitored
€ 4,616,757.22
of which cohesion funds
€ 4,605,907.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 1716722.19 | 1716722.19 | 37 |
2014 | 1973544.94 | 3690267.13 | 79 |
2015 | 915640.37 | 4605907.50 | 99 |
2016 | 0 | 4605907.50 | 99 |
2017 | 0 | 4605907.50 | 99 |
2018 | 10849.72 | 4616757.22 | 100 |
State of progress
Completed
Expected start: 12/11/2012
Effective start: 12/11/2012
Expected end: 09/09/2014
Effective end: 09/09/2014
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- IRCCS-FONDAZIONE PASCALE
- Beneficiary
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- Programme
- IROP CONV ERDF RENEWABLE ENERGY AND ENERGY CONSERVATION
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 4,605,907.50
- Payments on cohesion funds
- € 4,605,907.50
- Axis
- Asse II Efficienza energetica ed ottimizzazione del sistema
- Operational objective
- Potenziare e adeguare l'infrastruttura della rete di trasporto ai fini della diffusione delle fonti rinnovabili e della piccola e micro cogenerazione e il teleriscaldamento.