CUP: D86J13000800002
RECUPERO E VALORIZZAZIONE DEL TORRIONE E DEL CASSERO DELLA CINTA MURARIA MEDIEVALE DI CITERNA - RIVITALIZZAZIONE E RIFUNZIONALIZZAZIONE DELLE AREE VERDI DI PERTINENZA ED ABBATTIMENTO DELLE BARRIERE ARCHITETTONICHE E LIVELLO DELL'ACROPOLI
SUMMARY OF THE PROJECT
RECUPERO E VALORIZZAZIONE DEL TORRIONE E DEL CASSERO DELLA CINTA MURARIA MEDIEVALE DI CITERNA - RIVITALIZZAZIONE E RIFUNZIONALIZZAZIONE DELLE AREE VERDI DI PERTINENZA ED ABBATTIMENTO DELLE BARRIERE ARCHITETTONICHE E LIVELLO DELL'ACROPOLI
Implementation indicator
Superficie oggetto di intervento
- Target
- 230 mq
- Achieved
- 230 mq
Funding monitored
€ 299,960.89
of which cohesion funds
€ 239,968.71
Given name | Amount |
---|---|
Development and Cohesion Fund | 239968.71 |
Municipality | 59992.18 |
Payments monitored
€ 299,960.89
of which cohesion funds
€ 239,968.71
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 225.00 | 225.00 | 0 |
2016 | 167559.22 | 167784.22 | 55 |
2017 | 132176.67 | 299960.89 | 100 |
State of progress
Completed
Expected start: 15/11/2015
Effective start: 12/06/2015
Expected end: 25/09/2016
Effective end: 23/09/2016
Entities
- Planning body
- REGIONE UMBRIA
- Implementing body
- COMUNE DI CITERNA
- Beneficiary
- COMUNE DI CITERNA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE UMBRIA
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici